Attendees: Drew Bulfur, Fred Lavenberg, Brian Stevens, Jeff Earl, Marilyn Marshall, Charlie Windisch.
Meeting was called to order at 7:05pm.
- The minutes from the July 2022 meeting were approved.
- Third quarter water bill payment status: One household has not paid as of the meeting date. Further action will now be taken in an effort to obtain payment.
- Autopayment – The committee decided to put off for at least a quarter any additional steps of an autopay approach to paying the water bills.
- Fourth quarter bills will be sent out early September. Bills will be due October 1st.
- Communication between pump house and the reservoir: The communication takes place using a cell phone approach. The radios were upgraded in early August. This will improve the communication between the two buildings and lead to a constant water supply at the reservoir.
- Greensand filter replacement cost: A partial payment ($15K) was made to Culligan Water from our reserves. The rest will be covered by the forthcoming loan from the State Drinking water fund.
- Application to the state for the loan for the greensand filter is in the final stages. We have already been approved and the committee is working with the state towards completing the paperwork.
- The electrical box in the pump house needs to be replaced as soon as possible. The committee will address and get estimates.
Meeting was adjourned at 8:07pm.